July 19, 2017 Meeting Minutes

Budget & Finances: No issues to report

Lawyer continues to pursue outstanding balances.

Rail road ties work has not begun yet, still waiting on final prices from 84 landscaping.  Needed as soon as possible to ensure work is completed on time and within the current  budget.

Final contract language received from Green Meadows on snow removal, blizzard clause removed and replaced with a per storm cap which still carries some risk but limits the risk much better than previous contracts.

Painting has started

 